New industrial construction in Superior
Updated November 2026. Every industrial project we have found in Superior's plan commission minutes, building permits and state filings, new buildings and the biggest jobs first.
- Projects
- 3
- Permitted or under way
- 1
- Latest filing
- mid 2026
Industrial projects in Superior
- Permittedmid 2026New 2-story, 108'x80' warehouse/office buildingConstructing one (1) new 2-story, 108'x80' warehouse/office building. . . ***Conditions of Approval: 1.) This permit allows for the above-listed general construction work only. All other components of this project (land disturbing, plumbing, electrical, HVAC, fire suppression, sign installation, etc.) must be performed by a City-registered contractor of the corresponding type or other eligible party after first acquiring separate permits of the corresponding types. 2.) All contractors and subcontractors performing work on this project must be registered with the City and named on the corresponding permit to be eligible for work on this project.***49 E 2nd St, Superior
- Completeearly 2026Superior Lidgerwood Mundy - 3301 Winter StConstructing one (1) new manufacturing building with office spaces. . . ***Conditions of Approval: 1.) This permit allows for general construction work only. All other components of this project (land disturbing, plumbing, excavation, HVAC, fire suppression, signage, etc.) must be performed by a City-registered contractor of the corresponding type or other eligible party after first acquiring separate permits of the corresponding types. 2.) General contractor shall contact City Building Inspection to update permit to include contractors and subcontractors as they are added to this project.***3301 Winter St, Superior
- Completeearly 2026New Peterbilt Facility - 2929 Belknap StConstructing one (1) new 22,600 SF pre-engineered metal building with a truck service shop, parts warehouse, and offices. . . ***Conditions of Approval: 1.) This permit allows for general construction work only. All other components of this project (land disturbing, plumbing, electrical, HVAC, fire suppression, sign installation, etc.) must be performed by a City-registered contractor of the corresponding type or other eligible party after first acquiring separate permits of the corresponding types.***1423 Maryland Ave., Superior
Leads in Superior, all sectors
None of this place's leads is tied to a industrial project yet, so these are every sector's.
2 leads from plan commission and zoning meetings in Superior so far in 2026, and 4 in all of 2025.
2026 by kind: New construction 1, Other 1.
| 2025 | 2026 | |
|---|---|---|
| Early January to April | 0 | 1 |
| Mid May to August | 3 | 0 |
| Late September to December | 1 | 1 so far |
- 4.2 Review and approval of Vacant to Value: New Construction application for 18XX E 5th Street.V2VNC 26-01New construction · early 2026 · Stone Construction
- 4.1 Review and approval of Vacant to Value: New Construction application for 18XX E 10th Street.V2VNC 25-04New construction · late 2025 · New York Avenue Properties, LLC
- 4.2 Halvor Lines 25-01 Vacation request, review and recommendationOther · mid 2025
- 4.1 Review and approval of Vacant to Value: New Construction application for 16XX Ohio Avenue. V2VNC 25-03New construction · mid 2025
- Constructing one (1) new 18,000 ft² fire station.Other · mid 2025
1 more from the last four months: Other 1.