Marathon County healthcare construction
Updated November 2026. Every healthcare project we have found in Marathon County's plan commission minutes, building permits and state filings, new buildings and the biggest jobs first.
- Projects
- 9
- Declared value
- $111M
- New in 2026
- 2
- Latest filing
- late 2026
Stage
- Permitted 1
- Underway 1
- Complete 7
Projects by declared value
- over $50 million
- 1
- $10 million to $50 million
- 1
- $1 million to $10 million
- 5
- $100,000 to $1 million
- 2
Projects
- Underwaymid 2026Aspirus - Bed Tower AdditionEarly start permit application for the new Bed Tower Addition. This addition is roughly 95,000 square feet and located on the west side of the Aspirus property, just south of the main entrance333 Pine Ridge Blvd, Wausauover $50 million
- Completelate 2026333 Pine Ridge BlvdRenovation of the Entrance A Lobby, EEG, and Pet Ct areas333 Pine Ridge Blvd, Wausau$10 million to $50 million
- Permittedlate 2026Entry B Phase 1Interior remodel of level 00 and level 01 of Entry B at Aspirus Wausau Hospital.333 Pine Ridge Blvd, Wausau$1 million to $10 million
- Completemid 2026Observation/Admin/transportCommercial Addition & Alteration333 Pine Ridge Blvd, Wausau$1 million to $10 million
- Completemid 2026Aspirus - Breast HealthA 7,700 sf renovation on the 14,230 sf second floor of a non-separated mix-use B and AA3 occupancy existing building. The existing building is fully sprinklered. The scope of renovation is a Level 2 Alteration under the IEBC with a partial change of occupancy due to the conversion of an existing rehabilitation gym into group A assembly space. Outpatient use.1901 Westwood Center Blvd, Wausau$1 million to $10 million
- Completemid 2026226100 Rib Mountain DrCommercial Addition & Alteration226100 Rib Mountain Dr$1 million to $10 million
- Completemid 2026Aspirus - Plaza Dr. ClinicThe project consists of roughly 39,000 square feet of renovation to the Aspirus Plaza Drive clinic. Renovations are mainly architectural with flooring, painting, and ceiling tile upgrades.2720 Plaza Dr, Wausau$1 million to $10 million
- Completemid 2026515 S 32nd AveInterior repairs, some remodel for building. Creating separated tenant space in old clinic.515 S 32nd Ave, Wausau$100,000 to $1 million
- Completemid 2025333 Pine Ridge BlvdCommercial Addition & Alteration333 Pine Ridge Blvd, Wausau$100,000 to $1 million
Leads in Marathon County, all sectors
None of this place's leads is tied to a healthcare project yet, so these are every sector's.
85 leads from plan commission and zoning meetings in Marathon County so far in 2026, and 30 in all of 2025.
2026 by kind: Conditional use permit 17, Site plan review 15, Subdivision plat 11, Variance 7, Rezone 4, Development agreement 3, Certified survey map 2, Other 26.
| 2025 | 2026 | |
|---|---|---|
| Early January to April | 13 | 30 |
| Mid May to August | 13 | 34 |
| Late September to December | 4 | 21 so far |
- Discussion on approving a Conditional Use Permit for 151 McIndoe Street to allow for the construction of an assisted living facility in a Downtown Periphery Mixed- Use (DPMU) Zoning District. (Beacon Resources, LLC)Conditional use permit · mid 2026 · Beacon Resources, LLC
- Discussion and possible action approving the Specific Implementation Plan (SIP) for 1010 S. 16th AvenueOther · mid 2026
- Marathon County Highway Dept.Conditional use permit · mid 2026
- He explained the need for the garage building and how it would benefit the water utility, police department and parks department.Other · mid 2026
- requesting a front yard setback variance for a new additionVariance · mid 2026
- Partial Site Plan Application for Incredible Bank Located at 1130 E Grand AvenueSite plan review · mid 2026 · Incredible Bank
- Partial Site Plan Application for Imperial Industries Located at 202 Industrial Park AvenueSite plan review · mid 2026 · Imperial Industries
- Midwest Motor Condos LLC is requesting approval of a Planned Unit Development (PUD) overlay to allow development of a luxury motor condominium project consisting of fifteen individually owned storage units and a contractor condominium building.Site plan review · mid 2026
- Midwest Motor Condos LLC is requesting approval of a Planned Unit Development (PUD) overlay to allow development of a luxury motor condominium project consisting of fifteen individually owned storage units and a contractor condominium building.Subdivision plat · mid 2026
- Alliance Holdings, LLC has a pending contract for sale to the Green Tree Companies for its vacant parcels along and near the Villages northern boundary.Other · mid 2026
- East Nick Avenue Development (DISCUSSED AFTER ITEM 6. CONSENT AGENDA)Other · mid 2026 · PGA, Inc
- He discussed the status of the project and the security issues that exist with the water utility buildings.Other · mid 2026
- The project includes construction of a new approximately 9,000 square foot sales office and design center with an attached warehouse facility, along with a screened accessory storage structure for utility trailers and associated paved parking and driveway areas to relocate its current sales office from Weston to Rothschild.Site plan review · mid 2026
- Relocating the building twenty feet (20') closer to the front property line would result in the elimination of ten (10) parking spaces, reducing the total number of proposed off-street parking spaces from thirty (30) to twenty (20).Development agreement · mid 2026 · UDG Manager, LLC.
- Construction of a new transient hanger at the Central Wisconsin Airport. {570 Aviation Way}Other · mid 2026 · Central Wisconsin Airport
- Construction of a new manufacturing building in the 900 block of Indianhead Drive.Other · mid 2026 · Arow Global Corp
- Final Subdivision Plat for Hidden Ridge Estates located in Section 17 of the Town of Mosinee and within the City's extraterritorial area.Subdivision plat · mid 2026
- Gray’s Cedar Creek, LLC (Culver’s)Site plan review · early 2026
- Discussion on approving a Conditional Use Permit for 218 South 4th Street to authorize and allow construction of a Personal Storage Facility use in the Light Industrial (LI) Zoning District. (Dunwoody Storage)Conditional use permit · early 2026 · Dunwoody Storage
- (Jicinsky)(Krause) was carried to allow SPARC to install lights at the pickle ball courts.Other · early 2026
- (Hoes)(Carolfi) was carried to approve a Planning Commission recommendation to approve a driveway width variance request for First Choice recycling at 504 E Willow Drive allowing for two 60-foot-wide driveways.Variance · early 2026
- (Hoes)(Krause) was carried to approve a Planning Commission recommendation to approve a setback variance request for an accessory structure for Quality Electric at 409 W Willow Drive allowing for side lot line and back lot line setbacks of 10 feet.Variance · early 2026 · Quality Electric
- Wegner walked through the site plan along with vegitation, sound barrier walls and lighting.Site plan review · early 2026
- 7 story apartment complexConditional use permit · early 2026 · Beacon Resources, LLC
- Wegner walked through the site plan along with vegitation, sound barrier walls and lighting.Development agreement · early 2026
- (Schafer)(Carolfi) was carried to schedule a Public Hearing for the Discontinuation of the South Monroe Street right-of-way between East Clark Street and East Peach Street.Other · early 2026
- Midwest Motor Condos LLC is requesting approval of a Planned Unit Development (PUD) overlay to allow development of a luxury motor condominium project consisting of fifteen individually owned storage units and a contractor condominium building.Conditional use permit · early 2026
- Midwest Motor Condos LLC is requesting approval of a Planned Unit Development (PUD) overlay to allow development of a luxury motor condominium project consisting of fifteen individually owned storage units and a contractor condominium building.Rezone · early 2026 · Midwest Motor Condos LLC
- 7 story apartment complexOther · early 2026 · Beacon Resources, LLC
- Premier Property DevelopmentSite plan review · early 2026
- amend the Denyon Homes Developer’s agreement to include a firm commitment to build 10 houses by the end of 2029.Other · early 2026
- request approval of the Final Plat for the proposed The River on Maple Ridge SubdivisionSubdivision plat · early 2026
- Seedtime & Harvest LLC {Hunt Brothers Pizza}Other · early 2026
- Terra Consulting GroupSite plan review · early 2026
- Covenant Community Presbyterian ChurchSite plan review · early 2026
- Bauer’s 2nd Addition Final Plat– Town of SpencerSubdivision plat · late 2025
- A&D Contractors, LLCSubdivision plat · late 2025
- Rezoning 405 South 8th Avenue from (I) Institutional Zoning District to (MRM-20) Multi-Family Residential-20 Zoning District (City of Wausau Community Development Department and Community Development Authority)Other · mid 2025
- Discussion on approving a Conditional Use Permit for 2811 West Wausau Avenue to allow construction of a Multiplex (3-4 units per building) within the Two-Flat Residential-10 (TF-10) Zoning DistrictConditional use permit · mid 2025
- Vacating and discontinuing Pine Ridge Boulevard from North 28th Avenue to Westhill DriveOther · mid 2025
- Discussion on approving a Conditional Use Permit for 508 East Wausau Avenue to allow construction of an off-street parking lot within the Two-Flat Residential-10 (TF-10) Zoning DistrictConditional use permit · mid 2025
- Rezoning 1040 S 12th Ave from a TF-10 to a PUD to allow for 2 duplexes. (MAC Ventures)Other · mid 2025
- Glacier Meadows Concept Plan Overview given by Denyon Homes.Other · mid 2025
- Discussion and possible action for the Specific Implementation Plan for 920 N 1st St and 15 Fulton St, also known as Riverlife South (Wangard)Other · mid 2025
- (Carolfi)(Hoes) was carried on unanimous roll call vote to approve a DNR Grant Agreement for the construction of a new Public Shooting Range.Other · mid 2025
- A 7,842 SF REMODEL TO AN EXISTING MERCHANTILE OCCUPANCY TO AN EMERGENCY SHELTER. THE SHELTER WILL CONSIST OF A MEN'S SLEEPING ROOM FOR 40 OCCUPANTS, A WOMEN'S SLEEPING ROOM FOR 40 OCCUPANTS AND THREE SPECIAL NEEDS SLEEPING ROOMS. AN ADDITION WILL BE OFF THE FRONT OF THE BUILDING FOR A SMOKING AREA.Other · early 2025
- Interior finishes are getting updated. The Bar, Cooler are getting replaced. A new kitchen and outdoor deck will be builtOther · early 2025
- Updates presented. Access added, a park and pond.Other · early 2025
- Green Tree Meadows Plat – Town of Stettin/ City of WausauSubdivision plat · early 2025
- 50-unit apartment and community service tenant. Construction Type: V-A IA.Other · early 2025 · M+A Design
31 more from the last four months: Conditional use permit 7, Site plan review 5, Subdivision plat 5, Rezone 3, Variance 2, Certified survey map 1, Other 8.