New multifamily construction in Muskego
Updated November 2026. Every multifamily project we have found in Muskego's plan commission minutes, building permits and state filings, new buildings and the biggest jobs first.
- Projects
- 3
- New in 2026
- 1
- Proposed
- 1
- Approved
- 1
- Latest filing
- mid 2026
Multifamily projects in Muskego
- Proposedmid 2026W182 S8450 Racine AvenueThe new proposal is for 76 additional units with ten two-story townhomes with four units each for 40 units.W182 S8450 Racine Avenue, Muskego
- Withdrawnlate 2025Woodcrest ApartmentsThe petitioner is working with all the other owners to have one single enclosure on the far eastern edge of the site to limit the travel and minimize the damage and asphalt repair from the garbage truck.S86 W18600 Jean Drive, Muskego
- Approvedearly 2025Auto service and repairConditional use permitS83 W18390 Saturn Drive, Muskego
Recent plan commission items
3 in all: Conditional use permit 1, Site plan review 1, Other 1.
Multifamily leads in Muskego
1 multifamily leads from plan commission and zoning meetings in Muskego so far in 2026, and 3 in all of 2025.
2026 by kind: Site plan review 1.
| 2025 | 2026 | |
|---|---|---|
| Early January to April | 1 | 0 |
| Mid May to August | 0 | 1 |
| Late September to December | 2 | 0 so far |
- The new proposal is for 76 additional units with ten two-story townhomes with four units each for 40 units.Site plan review · mid 2026
- The petitioner is working with all the other owners to have one single enclosure on the far eastern edge of the site to limit the travel and minimize the damage and asphalt repair from the garbage truck.Other · late 2025
- BB Motors LLCConditional use permit · early 2025