Marshfield new construction projects and permits
Updated November 2026. Every project we have found in Marshfield's plan commission minutes, building permits and state filings, new buildings and the biggest jobs first.
- Projects
- 60
- Declared value
- $75M
- New in 2026
- 27
- Proposed
- 1
- Approved
- 5
- Permitted or under way
- 28
- Latest filing
- late 2026
So far in 2026 in Marshfield: 5 construction sites filed for stormwater coverage and 1 state building plan filed.
Projects in Marshfield
- Underwaylate 2026New Chipotle restaurantNew ground up freestanding cold, dark shell building for future quick serve Chipotle restaurant. Will have approval letter next week (3/23).1307 N Central Ave, Marshfield$1 million to $10 million
- Completelate 20263903 S Draxler DrNew 24,469 s.f. Fabrication facility to produce steel and aluminum parts, pieces, structures, frames, beds, supports used in the production assembly of service trucks (i.e. snow plow trucks, delivery trucks with cranes attached, etc)3903 S Draxler Dr, Marshfield$1 million to $10 million
- Underwaylate 2026New stand alone Panda ExpressThis is a proposal for a new stand alone Panda Express. For quick-service, dine-in, take-out, mobile ordering, and drive-through.1904 N Peach Ave, Marshfield$1 million to $10 million
- Completelate 20262503 E Heritage DrNew 22,044 s.f. large truck and semi-truck parts sales and service center including truck wash bay and parts storage. Has upper floor/mezzanine and the total s.f. including upper floor/mezzanine is 26,690 s.f.2503 E Heritage Dr, Marshfield$1 million to $10 million
- Underwaymid 2026NGA Site - MarshfieldNew Building Construction, Pre approved state plans.2628 E Yellowstone Dr, Marshfield$1 million to $10 million
- Completeearly 2026308 W 29th StNew PEMB for use as an airplane hangar on concrete footings and foundations, concrete slab. Insulated, heated building with steel stud wall buildout of office and bathroom space; sprinkled building308 W 29th St, Marshfield$1 million to $10 million
- Underwaymid 20262113/2115 Shortess DriveNew Construction Duplex2113/2115 Shortess Drive, Marshfield$100,000 to $1 million
- Underwaymid 20262228/2230 Shortess DriveNew Construction Duplex2228/2230 Shortess Drive, Marshfield$100,000 to $1 million
- Underwaymid 20262222/2224 Shortess DrNew Construction Duplex2222/2224 Shortess Dr, Marshfield$100,000 to $1 million
- Underwaymid 20262201/2203 Shortess DriveNew Construction Duplex2201/2203 Shortess Drive, Marshfield$100,000 to $1 million
- Underwaymid 20262205/2207 Shortess DrNew 1 & 2 Family Home2205/2207 Shortess Dr, Marshfield$100,000 to $1 million
- Underwaymid 20262221/2223 Shortess DrNew Construction Duplex2221/2223 Shortess Dr, Marshfield$100,000 to $1 million
Showing 12 of 60 in Marshfield. Narrow by sector or city above, or see them all in the tracker below.
Sectors
- Multifamily7
- Restaurant6
- Office6
- Retail5
- Industrial5
- Healthcare4
Projects by declared value
- $10 million to $50 million
- 2
- $1 million to $10 million
- 13
- $100,000 to $1 million
- 32
- under $100,000
- 2
Marshfield construction projects in the news
3 Marshfield projects have been in the news, 3 articles in all, from publishers including Hub City Times, OnFocus, cwbradio.com. Headlines open the publisher's article.
- Underway$10 million to $50 millionsoutheast corner of Galvin Avenue and East 24th StreetConstruction of new 99,000 sqft manufacturing building, PEMB on concrete foundation walls, concrete slab, metal sheeted insulated walls, membrane roofsoutheast corner of Galvin Avenue and East 24th Street, Marshfield
- Quality Tank Solutions Breaks Ground on Third Manufacturing Facility in Marshfieldcwbradio.com · August 2026
- Underway$1 million to $10 millionnew Chipotle restaurantNew ground up freestanding cold, dark shell building for future quick serve Chipotle restaurant. Will have approval letter next week (3/23).1307 N Central Ave, Marshfield
- Chipotle construction underway in MarshfieldOnFocus · June 2026
- Underway$1 million to $10 millionI-StateNew 69,049 sf (footprint), 78,873 sf truck assembly facility for large truck builds, complete with 2 large truck paint booths, 7-bay body shop, warehouse and 12 station assembly area. office areas on 2 levels, support the truck assembly operation and includes offices, break rooms, locker rooms, training rooms, sales, etc.Heritage Drive, Marshfield
- I State Truck Center project gets plan commission approvalHub City Times · October 2025
Leads in Marshfield
9 leads from plan commission and zoning meetings in Marshfield so far in 2026, and 10 in all of 2025.
2026 by kind: Conditional use permit 4, Rezone 1, Site plan review 1, Subdivision plat 1, Other 2.
| 2025 | 2026 | |
|---|---|---|
| Early January to April | 5 | 3 |
| Mid May to August | 1 | 6 |
| Late September to December | 4 | 0 so far |
- rezone the property from "CMU" Community Mixed Use to "PD" Planned Development, in conjunction with a property line adjustmentSite plan review · mid 2026 · the Boson Company
- exception to Section 18-35(7) of the zoning code to address the minimum pavement setbacks from the property lineConditional use permit · mid 2026 · BKV Group
- rezone the property from "CMU" Community Mixed Use to "PD" Planned Development, in conjunction with a property line adjustmentRezone · mid 2026 · the Boson Company
- review and approve a proposed amendment to the High School/Madison Elementary Campus Master Plan to allow for a new parking area and move the sand volleyball courtsOther · mid 2026
- requesting to have a Personal Storage Facility and also an exception to the required residential bufferyard (minimum opacity 0.80)Conditional use permit · early 2026
- Preliminary Subdivision Plat reviewSubdivision plat · early 2026
- requesting to have an outdoor eating area and also an exception to the 40 foot stacking requirementConditional use permit · early 2026
- Panda Express, Inc.Conditional use permit · late 2025
- New 69,049 sf (footprint), 78,873 sf truck assembly facility for large truck builds, complete with 2 large truck paint booths, 7-bay body shop, warehouse and 12 station assembly area. office areas on 2 levels, support the truck assembly operation and includes offices, break rooms, locker rooms, training rooms, sales, etc.Conditional use permit · late 2025 · Interstate Marshfield, LLC
- Construction of new 99,000 sqft manufacturing building, PEMB on concrete foundation walls, concrete slab, metal sheeted insulated walls, membrane roofConditional use permit · late 2025
- This conditional use permit allows the construction of a fourth accessory structure to be used as a personal greenhouse.Conditional use permit · mid 2025
- to allow for the construction of a non-residential accessory building prior to the construction of a principal structure for the property located at 311 East Heritage Drive (parcel 33-07387).Conditional use permit · early 2025 · (North Ridge Church)
- New 69,049 sf (footprint), 78,873 sf truck assembly facility for large truck builds, complete with 2 large truck paint booths, 7-bay body shop, warehouse and 12 station assembly area. office areas on 2 levels, support the truck assembly operation and includes offices, break rooms, locker rooms, training rooms, sales, etc.Other · early 2025 · I-State
- Campus Master Plan Update Request by Marshfield Fairgrounds Park to approve the five-year Campus Master Plan update for the Marshfield Fairground Park Campus Master Plan.Other · early 2025
1 more from the last four months: Other 1.